Watershed Management Program

Ongoing Public Notifications

Pasco County
Public Notification/Comment Dates: -

Preliminary Floodplain Results Public Meeting Calendar

These public meetings provide citizens a chance to learn about the data and science used to determine the flood hazard areas, to view the preliminary floodplain results and to ask questions and provide comments.

  • Meeting times and locations vary — click on watershed names for details
  • All technical presentations are held at our Brooksville Headquarters unless otherwise noted
  • Technical datasets and peer review reports can be obtained by contacting: Jessica Hendrix, Mapping & GIS Section, (352) 269-6442, or downloaded directly from the District’s ShareFile site.

Citrus

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
Cardinal Lane 2011-07-14 2011-11-01 2012-09-25
Center Ridge 2010-05-26 2010-08-31 2011-08-30
Chassahowitzka River 2021-09-10 2022-12-06 2024-05-21
Crystal River (Unincorporated) 2010-01-25 2010-05-04 2010-08-24
East Citrus Withlacoochee River 2015-03-12 2015-08-04 2019-05-21
Homosassa River (North/South & South Fork) 2013-01-14 2013-08-22 2014-06-24
North Citrus Withlacoochee River 2021-08-04 2022-06-29 2024-06-25
Tsala Apopka 2011-05-10 2011-09-01 2011-12-20

DeSoto

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
Deep Creek Gully 2010-02-17 2010-07-29 2010-12-14
Thornton Branch 2010-09-15 2011-01-11 2011-06-28

Hardee

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
Alligator Branch 2009-12-15 2010-07-07 2010-12-14
Buzzards Roost Run 2009-12-15 2010-07-07 2010-12-14
City of Wauchula 2009-12-15 2010-07-07 2010-12-14
Horse Creek 2010-01-21 2010-07-07 2010-12-14
Thompson Branch 2009-12-15 2010-07-07 2010-12-14

Hernando

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
Blue Sink 2008-08-22 2008-10-30 2009-02-24
Bystre Lake 2009-03-25 2009-06-16 2010-01-26
Centralia 2009-05-11 2009-07-30 2009-12-15
Chassahowitzka 2008-10-06 2009-03-12 2009-09-29
Croom 2008-08-08 2008-10-30 2009-01-26
Eastern Hernando 2008-09-24 2008-11-12 2009-02-24
Little Withlacoochee 2008-09-24 2008-11-12 2009-01-26
Lizzie Hart Sink 2008-08-07 2008-10-01 2008-11-18
McKethan 2008-08-06 2008-10-30 2009-09-29
Oman Quarry/Indian Creek 2008-08-05 2008-10-28 2008-12-16
Peck Sink 2015-02-11 2015-07-09 2018-08-28
Powell 2008-08-08 2008-10-28 2008-12-16
Spring Hill Lakes / Aripeka 2008-08-29 2008-11-12 2009-04-28
Squirrel Prairie 2009-12-16 2013-10-29 2017-01-24
Toachodka 2008-06-25 2008-10-28 2009-03-31
Tooke 2008-10-13 2009-02-26 2009-05-20
Weeki Wachee Prairie 2008-09-26 2009-03-12 2010-01-26
Willow Sink 2009-12-15 2009-07-30 2009-12-15
Wiscon 2008-09-10 2009-02-26 2009-06-23

Highlands

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
Carter Creek 2013-11-19 2014-06-24
Highlands Hammock 2024-09-27
Highlands Lakes 2011-05-26 2011-10-27 2011-12-20
Jack Creek 2023-12-12
Lake Placid 2014-09-11 2015-03-31
Sebring

Hillsborough

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
Alafia River 2020-01-28 2020-09-22
Bullfrog Creek
Curiosity Creek
Cypress Creek 2016-10-25
Delaney Creek 2017-05-30
Duck Pond 2023-04-25
East Lake 2022-07-26
Hillsborough River / Tampa Bypass Canal (TBC) 2022-07-26
Little Manatee River
Northwest Five 2017-06-27
Pemberton Creek / Baker Canal 2021-12-14
Plant City 2022-01-13 2022-02-15 2022-10-18
Silver Twin Lakes 2022-06-21

Levy

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
City of Williston 2016-08-26 2017-07-13
Town of Bronson 2015-04-02 2015-10-08

Manatee

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
Bowlees Creek 2021-05-10 2021-11-16
Braden River 2011-10-12 2012-04-05 2013-05-21
Buffalo Canal/Frog Creek 2010-02-11 2010-06-15 2010-10-26
City of Bradenton 2017-11-14
Cow Pen Slough
Gamble Creek 2011-04-04 2011-07-19 2012-06-26
Mill Creek 2018-06-19 2021-04-27
Pearce Drain / Gap Creek 2021-11-16

Marion

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
Blichton 2010-11-30 2011-05-24 2011-11-29
Cotton Plant 1 2010-11-30 2011-05-24 2011-11-29
Cotton Plant 2 2010-11-30 2011-05-24 2011-11-29
Cotton Plant 3 2010-11-30 2011-05-24 2011-11-29
Flemington 2010-09-22 2011-04-26 2011-10-25
Gum Swamp / Big Jones Creek
Hog Prairie 2010-09-22 2011-04-26 2011-10-25
Lake Stafford East / Priest Prairie Drain 2015-08-20 2015-12-15
Martel 2010-11-30 2011-05-24 2011-11-29
NW Ocala 2010-09-22 2011-04-26 2011-10-25
Rainbow River (Blue Run)
SR 200 2010-11-30 2011-05-24 2011-11-29
West Marion 2015-08-20 2015-12-15
West Ocala 2013-10-11 2014-04-16 2015-04-28
Withlacoochee River Region 2010-04-13 2010-10-06 2010-12-14

Pasco

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
Anclote East 2008-10-03 2009-03-11 2011-04-26
Anclote West 2015-10-01 2017-08-07 2018-07-28
Cypress Creek
Double Hammock 2016-09-08 2017-06-26 2018-05-22
Duck Lake 2017-02-03 2017-11-16 2018-05-22
East Pasco 2008-09-16 2009-01-15 2010-02-22
Hammock Creek 2008-10-02
Lower Coastal 2018-03-29 2018-09-10 2019-10-29
New River / Upper Hillsborough 2013-11-21 2014-05-22 2015-01-27
Pithlachascotee River/Bear Creek 2013-04-16 2014-04-29 2017-04-25
Port Richey 2012-09-04 2013-01-14 2015-03-31
Trout Creek

Pinellas

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
Allens Creek
Alligator Creek 2012-11-15 2013-07-25 2013-11-19
Brooker Creek 2021-10-06 2023-08-10 2024-06-25
City of Oldsmar 2017-11-30 2018-11-13
City of Seminole 2023-09-21 2023-09-05 2024-03-26
City of St. Petersburg 2023-04-12 2024-03-26
Coastal Zone 5
Cross Bayou
Curlew Creek
Joe's Creek
Klosterman Bayou 2023-09-14 2024-01-25
Lake Tarpon 2023-11-28 2023-08-10 2024-03-26
McKay Creek
Roosevelt Creek
South Creek 2024-05-21
Starkey Road Basin
Sutherland Bayou

Polk

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
Christina 2009-10-27 2010-01-12 2010-12-14
Davenport 2021-09-23 2022-03-15 2023-01-24
Haines City 2020-10-30 2022-05-24
Itchepackesassa Creek
Mulberry 2013-10-30 2014-01-21 2014-06-24
Peace Creek 2009-12-07 2012-12-11 2013-02-26
Polk City 2011-08-01 2011-09-29 2012-09-25
Upper Peace River - Homeland 2014-10-24 2014-10-29 2016-01-19

Sarasota

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
Alligator Creek 2009-10-20 2010-01-06 2011-10-25
Hudson Bayou 2009-09-16 2009-12-09 2011-03-29
Island Of Venice 2009-10-20 2010-01-05 2011-11-29
North Port / Big Slough Canal 2011-01-26 2011-12-06 2012-05-22
Roberts Bay (Curry Creek / Hatchett Creek) 2009-10-20 2010-01-05 2012-05-22
Whitaker Bayou 2009-09-16 2009-12-09 2011-10-25

Sumter

Watershed Technical presentation to peer review consultant Technical dataset available Peer review report available Public meeting date Governing Board approved
Big Prairie 2013-04-08 2013-12-12 2014-06-24
Bushnell 2016-07-08 2016-09-22 2017-12-12
Gant Lake 2014-01-08 2014-02-19 2014-08-26
Jumper Creek 2017-09-21 2018-04-12 2019-05-21
Little Jones Creek/Wildwood 2021-07-14 2022-01-13 2023-02-28
Nichols Pond 2020-11-09 2022-04-26