Peace River Cumulative Impact Assessment
Timeline
Major project tasks of the Peace River Cumulative Impact Study along with a preliminary schedule is shown below. The schedule will be periodically updated as progress is made.
Task 1 - Literature Review, Data Collection and Detailed Scope of Work
Task 1 is expected to last from 3 to 6 months.
Task 2 - Description of Historical Changes
Task 2 is expected to last from 3 to 6 months depending on data assimilation. This phase may proceed concurrently with the latter stages of Task 1.
Task 3 - Identification and Analysis of Factors Causing Changes
Task 3 is expected to last from 3 to 6 months. This phase may proceed concurrently with the latter stages of Task 2.
Task 4 - Evaluate Regulatory Effectiveness
Task 4 is expected to last from 1 to 3 months. This phase may proceed concurrently with the latter stages of Task 2.
Task 5 - Technical Report
Task 5 is expected to last up to 3 months.
Task 6 - Meetings
Task 6 is expected to occur periodically throughout the project duration (12 months).